KPI Green Energy Commissions Additional 65.1 MWp Solar, Wind Capacity in Gujarat
KPI Green Energy has commissioned an additional 65.1 MWp of solar and wind capacity in Gujarat, taking the cumulative commissioned capacity under its 370 MW/677 MWp Hybrid IPP project at Bharuch to 575.8 MWp.
November 27, 2026. By Mrinmoy Dey
KPI Green Energy, a part of KP Group, has announced that the company has commissioned further capacity of 65.1 MWp, comprising 52.5 MWp of solar and 12.6 MW of wind capacity, under its 370 MW/677 MWp Hybrid Power Project (IPP) at Bharuch, Gujarat.
With the commissioning of the aforesaid capacity, the company has cumulatively energised 575.8 MWp out of 677 MWp capacity under the said Hybrid IPP Project, comprising 501.7 MWp of solar and 74.1 MW of wind capacity, KPI Green Energy said in a regulatory filing.
It further added that the project is being developed by the company as an Independent Power Producer (IPP) under a long-term Power Purchase Agreement with Gujarat Urja Vikas Nigam (GUVNL).
This addition brings the Hybrid IPP Project closer to full commissioning. With this, the company's cumulative energised Independent Power Producer (IPP) capacity has increased to 1.41 GWp, out of its total IPP portfolio of 3.22 GW, the company stated.
“The company remains focused on the timely execution of its project pipeline, as each phase of capacity commissioned under long-term PPAs adds to its stable, annuity-based revenue base, improving cash-flow visibility and supporting long-term value creation for its stakeholders,” it said.
Under the KP 3.0 strategic roadmap, KP Group is targeting the development of 10 GW of owned IPP capacity by FY32.
With the commissioning of the aforesaid capacity, the company has cumulatively energised 575.8 MWp out of 677 MWp capacity under the said Hybrid IPP Project, comprising 501.7 MWp of solar and 74.1 MW of wind capacity, KPI Green Energy said in a regulatory filing.
It further added that the project is being developed by the company as an Independent Power Producer (IPP) under a long-term Power Purchase Agreement with Gujarat Urja Vikas Nigam (GUVNL).
This addition brings the Hybrid IPP Project closer to full commissioning. With this, the company's cumulative energised Independent Power Producer (IPP) capacity has increased to 1.41 GWp, out of its total IPP portfolio of 3.22 GW, the company stated.
“The company remains focused on the timely execution of its project pipeline, as each phase of capacity commissioned under long-term PPAs adds to its stable, annuity-based revenue base, improving cash-flow visibility and supporting long-term value creation for its stakeholders,” it said.
Under the KP 3.0 strategic roadmap, KP Group is targeting the development of 10 GW of owned IPP capacity by FY32.