Production Performance of Oil & Natural Gas sector

Review for the month of November, 2013

December 24, 2013. By Moulin

Crude Oil production- performance 

Month / Period Planned Target (TMT) Actual Production (TMT) %age achievement Surplus(+) Shortfall(-) Vis-à-vis target (%age) Surplus(+) Shortfall(-) over last year   (%age) 
November, 2013* 3323.000 3141.427 94.5 -5.5 1.1
April-November, 2013* 25936.000 25159.510 97.0 -3.0 -0.9
April-November, 2012 25390.449

 

  • Company-wise achievments

 

Company / State Planned Target (TMT) Actual Production (TMT) %age achievement Surplus(+) Shortfall(-) (%age)
ONGC 2058.000 1805.320 87.7 -12.3
Gujarat 410.000 399.068 97.3  
Andhra Pradesh 21.000 24.043 114.5  
Tamil Nadu 18.000 18.220 101.2  
Assam 103.000 102.743 99.8  
Offshore 1506.000 1261.246 83.7  
         
OIL 321.000 295.700 92.1 -7.9
Assam 320.000 293.600 91.8  
Arunachal Pradesh 1.000 2.100 210.0  
         
PRIVATE/JVC 944.000 1040.407 110.2 10.2
         
TOTAL 3323.000 3141.427 94.5 -5.5

 

  • Reasons for Shortfall

 

Company / State Reasons for shortfall
ONGC (Offshore) Closure of wells to maintain lift Gas pressure due to engine replacement and over hauling of Process Gas Compressor (PGC) at Heera, increased water cut in well B-173A#2YH affected production.  Less than anticipated oil gain from new development wells of D-1 field,  delay in commissioning of B-193 process platform affected production. Delay in execution of G-1 development project. Less than anticipated oil gain from marginal fields development wells & side track wells.
ONGC (Gujarat) Less than anticipated oil gain from workover and new development wells affected production. Frequent GEB power shutdown, ageing of fields resulting decline in reservoir pressure & increased water cut affected production.
OIL (Assam) Consequential effect of bandhs and blockades. 
Pvt./JVCs (Arunachal Pradesh) Production from KSG#46 ceased due to sudden increase in water cut. Further production from wells KSG#29, 34, 57, 11,29,58,65 and 66 has declined due to sand ingress and increase in water cut.
Pvt./JVCs (Gujarat) No Oil productions as the wells are ceased in Dholasan & Bhandut field.  Breakdown of pump at ONGCunloadng facility. High water cut in producing wells in CB-ON/7.  Natural decline.  Water ingress issues in wellbores.

 

Natural Gas Production

 

Month / Period Planned Target (MCM) Actual Production (MCM) %age achieve-ment Surplus(+) Shortfall(-) Vis-à-vis target   (%age) Surplus(+) Shortfall(-) over last year     (%age)
November, 2013* 3243.060 2893.282 89.2 -10.8 -11.3
April- November, 2013* 25551.867 23680.411 92.7 -7.3 -15.6
April-November, 2012 28048.105

MCM: Million Cubic Metres.    

 

  • Company- Wise Achievments

 

Company / State Planned Target (MCM) Actual Production (MCM) %age achievement Surplus(+) Shortfall(-) (%age)
ONGC 1990.050 1916.136 96.3 -3.7
Gujarat 113.820 126.508 111.1  
Rajasthan 1.230 1.479 120.2  
 Andhra Pradesh 83.870 96.708 115.3  
Tamil Nadu 97.560 108.617 111.3  
Assam 38.240 37.461 98.0  
Tripura 72.520 61.913 85.4  
Mumbai High Offshore 1582.810 1483.450 93.7  
         
OIL 224.820 226.402 100.7 0.7
Assam 202.580 205.262 101.3  
Arunachal Pradesh 1.200 1.518 126.5  
Rajasthan 21.040 19.622 93.3  
         
PRIVATE/JVC 1028.190 750.744 73.0 -27.0
Onshore $ 113.103 102.293 90.4  
Offshore 915.087 648.451 70.9  
         
TOTAL 3243.060 2893.282 89.2 -10.8

$: Including Coal Bed Methane production.

 

  • Reasons for Shortfall

 

Company / State Reasons for shortfall
ONGC (Offshore) Delay in commissioning of B-193 & SB-14 process platform affected production.  Delay in execution of G-1 development project.
ONGC (Assam) Lack of consumers.
ONGC (Tripura) Less offtake by consumers.
OIL(Rajasthan) Less than the committed withdrawal of Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL).
Pvt./JVCs (West Bengal) CBM produced in samll quantities are being internally used and flared as no market in near vicinity.
Pvt./JVCs (Gujarat) Less oil production due to breakdown of pump at ONGC unloadng facility.  High water cut in producing wells in CB-ON/7.  Natural decline.  Water ingress issues in wellbores.  No gas production from the field as wells have ceased due to water loading in Boala.  Gas production was ceased w.e.f. 10.11.2012 as per GOI directives prior to field abandonment in CB-ONN-2000/2. 
Pvt./JVCs  (Jharkhand) Incidentally produced CBM is being sold in small quantities.
Pvt./JVCs  (Off-shore) Tapti gas production is less than budget due to non delivery of expected volumes from infill wells and MTA # 3 early water breakthrough followed by loading. A total of 9 wells in D1,D3 and 2 wells in MA have ceased to flow due to water /sand ingress in KG-SWN-98/3 field.  Loading of wells, delayed well services activities, delayed delivery of PJ and PL infill wells and closure of MA wells due to leak observed in the MA riser.

 

Refinery Production

 (In Terms of Crude Throughput )

Month / Period Planned Target (MCM) Actual Production (MCM) %age achieve-ment Surplus(+) Shortfall(-) Vis-à-vis target   (%age) Surplus(+) Shortfall(-) over last year     (%age)
November, 2013* 17818.000 17802.709 99.9 -0.1 -5.0
April- November, 2013* 147724.000 147968.305 100.2 0.2 2.5
April-November, 2012 144303.636

Note: RIL (SEZ) production figures for  Sept` 2013 are revised from 3089  TMT to 3045 TMT & Oct` 2013 prorated figures revised from 3151 TMT to 3192 and Nov` 2013 figures are on prorated basis.

The crude throughput in IOC (Guwahati,  Haldia,Digboi, Barauni Panipat & Bongaigaon), BPCL (Mumbai, Kochi), HPCL (Mumbai), NRL (Numaligarh), ONGC (Tatipaka), BORL (Bina), HMEL (Bhatinda) & RIL (SEZ)  refineries have exceeded their planned target.

The crude throughput in IOC (Gujarat & Mathura), HPCL (Visakh), CPCL (Manali & Narimanam),  MRPL (Mangalore,) RIL (Jamnagar) & Essar  refineries was less than their planned target.

 

Company / State Reasons for shortfall
IOCL, Gujarat Throughput is restricted due to problem in Crude Unit furnace & High Black Oil inventory on account of lower Bitumen demand.
IOCL, Mathura Throughput is lower because of shifting of planned shutdown from Aug-Sep`13 to Oct-Nov`13.
HPCL, Visakh Low crude throughput for ISD (VGO) management.
CPCL, Manali Low crude throughput due to Ref-I shutdown based on economics.
CPCL, CBR Low thruput due to maintain LSHS production in line with planned offtake and crude mix.
MRPL,Mangalore LUnits were under shutdown due to Refinery black out.

 

  • Refinery Capacity Utiliztion

 

Month Utilisation (%) Period Utilisation (%)
November, 2013* 100.7 April- November, 2013 102.9
 November, 2012 107.0 April- November, 2012 101.

 

Tags:
Please share! Email Buffer Digg Facebook Google LinkedIn Pinterest Reddit Twitter
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
 
 
Next events
 
 
Last interviews
 
Follow us