Home › Renewable energy ›NTPC Green Energy Issues EoI for 5 MW Solar Plant with 4 MW/12 MWh BESS in Great Nicobar Island
NTPC Green Energy Issues EoI for 5 MW Solar Plant with 4 MW/12 MWh BESS in Great Nicobar Island
NTPC Green Energy has invited Expressions of Interest (EoI) for developing a 5 MW solar PV plant with a 4 MW/12 MWh battery energy storage system (BESS) at Great Nicobar Island. Bid submission ends on April 18, 2025.
March 13, 2025. By Mrinmoy Dey

NTPC Green Energy has invited Expression of Interest (EoI) for development and installation of Solar PV Plant with Battery Energy Storage system (BESS) at Great Nicobar Island.
The tentative capacity presently being targeted through this EOI has been planned up to 5 MW of solar PV plant with BESS capacity up to 4 MW/12 MWh.
The project must be completed in 6 months.
The last date for the submission of bids is April 18, 2025. The techno-commercial bids will be opened on April 21, 2025.
The scope of work includes EPC of Ground mounted Solar PV project with BESS, transmission of power from Power plant to existing substations and study of energy requirement and existing transmission system of island and suggest capacity of renewable energy project and requirement of energy storage.
The companies will be required to come up with a detailed plan and past project experience of establishing of renewable projects and BESS project.
The bidder must be an entity who has earlier successfully executed the solar plant and BESS, either combined or separately, based on which the project(s) has/have been under execution/implementation or have been completed and are under successful operation.
The responses received in the EoI will be identification of various prospective bidders/companies technically and commercially capable to install renewable projects at Great Nicobar Island and for the formulation of specifications, qualifying criteria and techno-commercial terms and conditions for the tender.
The tentative capacity presently being targeted through this EOI has been planned up to 5 MW of solar PV plant with BESS capacity up to 4 MW/12 MWh.
The project must be completed in 6 months.
The last date for the submission of bids is April 18, 2025. The techno-commercial bids will be opened on April 21, 2025.
The scope of work includes EPC of Ground mounted Solar PV project with BESS, transmission of power from Power plant to existing substations and study of energy requirement and existing transmission system of island and suggest capacity of renewable energy project and requirement of energy storage.
The companies will be required to come up with a detailed plan and past project experience of establishing of renewable projects and BESS project.
The bidder must be an entity who has earlier successfully executed the solar plant and BESS, either combined or separately, based on which the project(s) has/have been under execution/implementation or have been completed and are under successful operation.
The responses received in the EoI will be identification of various prospective bidders/companies technically and commercially capable to install renewable projects at Great Nicobar Island and for the formulation of specifications, qualifying criteria and techno-commercial terms and conditions for the tender.