NETC’s 400kV Palatana- Silchar- Bongaigaon Double circuit corridor in North Eastern part of India – Challenges & their mitigation
In India power utilities are under tremendous pressure to meet the growing demand for power as the country is on a firm footing on the development trajectory to become one of the largest economies of the world.
April 27, 2022. By News Bureau

Abstract – In India power utilities are under tremendous pressure to meet the growing demand for power as the country is on a firm footing on the development trajectory to become one of the largest economies of the world. To meet the increasing energy demand coupled with the fact that the load centers being far away from generating stations, transmission lines are to be constructed and maintained in all types of terrain. The task of maintaining these transmission lines becomes very arduous and difficult, if the terrain is hilly with steep gradients covered by dense tropical rainforest bordering river valleys. Such type of terrain poses many threats to the security of the Transmission system which entails various cost-effective and innovative techniques of maintenance protocol.
North East Transmission Company (NETC) is entrusted with maintenance of its 662.8 Km, 400 kV Double Circuit transmission corridor through similar difficult hilly & dense forest terrain of the States of Tripura, Meghalaya and Assam in the North Eastern Region (NER) of India. Some of the forest terrains are also inhabited by wild animals mainly Elephants & Leopards. The transmission line crosses two major rivers namely Brahmaputra & Barak. The mighty Brahmaputra river with its source in Tibet, flows down through the steep Southern Himalayas with great speed and flows with huge discharge & speed during monsoon season from its numerous tributaries causing erosion, flash floods and siltation leading to frequent changes of its course. Similarly, the Barak river also causes flood and erosion. The terrain consists of various types of soil viz., laterite, alluvial, loamy etc. and is prone to sinking and landslides due to steep gradient and soil characteristics. The transmission lines traverses through terrain with the high rainfall, wind zones of V & VI and high Isokeraunic level. Increasing threat from insurgency adds up to the multiplicity of problems.
This paper strives to describe in detail various types of challenges being faced and their mitigation measures adopted by NETC.
Keywords: Oil and Natural Gas Commission (ONGC), Tower Footing Resistance (TFR),Random Rubble Masonry (RRM),Emergency Restoration System (ERS),Reinforcement Cement Concrete (RCC),Reinforcement Cement Bored (R.C. Bored), Transmission Line Arrestors (TLA), Punctured Insulator Detection (PID), Central Electricity Regulatory Commission (CERC), Normative Annual Transmission System Availability Factor (NATAF), Isokeraunic level, North Eastern Region (NER), Palisading work, hydrophobicity, arterial roads, silverish coating fortified, Pile Foundation, Jhum Burning.
1- INTRODUCTION- NETC’S TRANSMISSION LINE CORRIDOR
NETC’s transmission line corridor is evacuating almost one third of the power demand of the North Eastern Region of India along with exporting power to a neighboring country. A map showing transmission line corridor in NER [Reference 1] is exhibited in Fig-1.
North East Transmission Company (NETC) is entrusted with maintenance of its 662.8 Km, 400 kV Double Circuit transmission corridor through similar difficult hilly & dense forest terrain of the States of Tripura, Meghalaya and Assam in the North Eastern Region (NER) of India. Some of the forest terrains are also inhabited by wild animals mainly Elephants & Leopards. The transmission line crosses two major rivers namely Brahmaputra & Barak. The mighty Brahmaputra river with its source in Tibet, flows down through the steep Southern Himalayas with great speed and flows with huge discharge & speed during monsoon season from its numerous tributaries causing erosion, flash floods and siltation leading to frequent changes of its course. Similarly, the Barak river also causes flood and erosion. The terrain consists of various types of soil viz., laterite, alluvial, loamy etc. and is prone to sinking and landslides due to steep gradient and soil characteristics. The transmission lines traverses through terrain with the high rainfall, wind zones of V & VI and high Isokeraunic level. Increasing threat from insurgency adds up to the multiplicity of problems.
This paper strives to describe in detail various types of challenges being faced and their mitigation measures adopted by NETC.
Keywords: Oil and Natural Gas Commission (ONGC), Tower Footing Resistance (TFR),Random Rubble Masonry (RRM),Emergency Restoration System (ERS),Reinforcement Cement Concrete (RCC),Reinforcement Cement Bored (R.C. Bored), Transmission Line Arrestors (TLA), Punctured Insulator Detection (PID), Central Electricity Regulatory Commission (CERC), Normative Annual Transmission System Availability Factor (NATAF), Isokeraunic level, North Eastern Region (NER), Palisading work, hydrophobicity, arterial roads, silverish coating fortified, Pile Foundation, Jhum Burning.
1- INTRODUCTION- NETC’S TRANSMISSION LINE CORRIDOR
NETC’s transmission line corridor is evacuating almost one third of the power demand of the North Eastern Region of India along with exporting power to a neighboring country. A map showing transmission line corridor in NER [Reference 1] is exhibited in Fig-1.
This 400 kV transmission line corridor has been envisaged to evacuate power from ONGC Tripura Power Company’s (OTPC) Palatana Gas Based Combined Cycle Power Project of 2x 363.3 MW in Tripura state. NETC has constructed 662.8 km of 400 kV Palatana- SilcharBongaigaon Double circuit line as detailed below
i) 400 kV Palatana- Silchar D/c line (247. 39 km)
ii) 400 kV (First circuit of D/C) Silchar- Byrnihat line (214.41 km)
iii) 400 kV (Second circuit of D/C) Silchar- Azara line (256.41 km)
iv) 400 kV (First circuit of D/C) Azara - Bongaigaon line (159 km)
v) 400 kV (Second circuit of D/C) Byrnihat-Bongaigaon line (201 km)
NETC’s transmission line corridor is exhibited in Fig-2.
2- CHAPTER 2- CHALLENGES
The task of maintaining the transmission line corridor with 100% availability is a prime concern. NETC is facing following major challenges
i) Vulnerability of line due to exposure of tower foundations because of land slide & rains. The transmission line is traversing through Assam and Meghalaya having highest rainfall to the tune of about 3 to 5 times the average rainfall in India. The average annual rainfall in India is 300- 650 millimetres. The details of rainfall in different states of NER [Reference 2] is shown below at Table- 1.
The task of maintaining the transmission line corridor with 100% availability is a prime concern. NETC is facing following major challenges
i) Vulnerability of line due to exposure of tower foundations because of land slide & rains. The transmission line is traversing through Assam and Meghalaya having highest rainfall to the tune of about 3 to 5 times the average rainfall in India. The average annual rainfall in India is 300- 650 millimetres. The details of rainfall in different states of NER [Reference 2] is shown below at Table- 1.
ii) Submergence of towers in low lying areas
iii) Tower endangerment during high wind & cyclones and changing course of rivers
iv) Outages due to severe lightning in hilly terrains with high soil resistivity
v) Transient fault & safety threat due to fast growth of vegetation and bamboo trees on hillsidesdue to the climatic condition of NER, and local tradition of subsequent burning of these under transmission lines
vi) Impact on the life of transmission line and Outages due to rapid industrial pollution. In addition to the above mentioned environmental & climatic challenges, there are many local & social challenges related to insurgency, theft, Right of Way etc.
3- CHAPTER-3 MEASURES ADOPTED TO MITIGATE THESE CHALLENGES
3.1 Temporary and Permanent Wall Protection
In the year 2018, the State of Tripura experienced unprecedented heavy monsoon with incessant rains in the month of June. The intensity of rain was so severe that within a time span of 7 – 10 days the free flowing rain water caused very heavy landslides in the entire hilly stretch of Tripura State resulting in number of road blockades in the Inter-State National Highway including some arterial roads.
Due to above landslide, 15(Fifteen) tower locations were badly affected and 8 (Eight) tower locations became vulnerable. This line being the only high-capacity line for evacuation of power from a 726.6 MW Generation Plant, any break down like tower collapse etc. would have caused outage of the Plant resulting in severe power crisis in the North Eastern Region. This emphasized immediate temporary measure to protect these vulnerable towers by providing bamboo palisade in multi steps along with empty cement bags filled with earth were taken in all these locations for providing minimum protection. Sufficient plantation was also done in the eroded sides of the locations to retain the soil.
However, as the measures taken were temporary in nature during that difficult time, Random Rubble Masonry (RRM) walls were subsequently constructed in 8 (Eight) badly affected towers locations before the onset of next monsoon to provide permanent protection. More plantation work is also being continued in these locations to increase the stability of the soil and to reduce erosion. The severity of landslides, temporary and permanent arrangement adopted in few locations is exhibited below in Figures 3A, 3B & 3C respectively.
3.2 Stub encasement & additional anti rust painting of tower legs in water logged areas
Some sections of the transmission lines (i.e. around 300 towers) remain submerged up to 7 (seven) months in a year in the low lying area in the State of Assam causing corrosion and rusting in the stub. For permanent eradication of this problem, the stubs of these towers were encased by raising the chimney heights by providing RCC up to various heights (max. up to 1.5 meters) depending upon the submergence water level of the towers. Further after encasement, in the towers where submergence level was beyond 1.5 meters, tower legs were painted up to the height of 3.0 meters with silverish coating fortified with Zinc & other metallic powder (MOSIL ZS – 44 & MOSIL RCH – 100) for prevention of rust and corrosion.
3.3 Adoption of Pile foundations for towers under threat due to river changing its course.
The Byrnihat / Azara – Bongaigaon section of the line is crossing the Brahmaputra River in the state of Assam.
The crossing involves 2 nos. well foundation locations as exhibited in Figure 4A, 1 no. pile foundation location and 2 nos. anchor tower locations on open cast foundation having depth of 3 meters with total crossing distance of 2.564 km. The Brahmaputra River is the largest river in the Indian sub-continent with very high velocity and 10th largest in the world in terms of discharge and known for its character of shifting its course. Fig: 4A
One of the anchor tower locations on the right bank of the river was 137 meters away from the river bank edge during construction in 2010. Subsequently, because of continuous erosion of the bank the distance reduced to 10 meters in the year 2016 which was 137 meters during 2010 as exhibited in Figure 4B. During the year 2016, this Anchor Tower location also got submerged by river water. Considering the fact that any further shifting of bank line or formation of any whirl pool in this area may cause a problem to the stability of the Anchor Tower foundation, this location was shifted to a safer location with pile foundation as per details indicated below in Table2. Prior to shifting, to protect this location from the continuous river bank erosion, Bamboo Palisading work had to be provided at the river bank face as a temporary protection measure as exhibited in Figure 4C.
For smooth and accident-free work of pile foundation, one of the circuits which was directly above the new pile foundation under construction had to be shifted by using an Emergency Restoration System (ERS) tower as exhibited in Figure 4D. Subsequently, on completion of the pile foundation the entire work of tower erection and final stringing was carried out by keeping one of the circuits continuously charged as per requirement so as to keep the power flow through this line intact. All tower foundations have been designed with adequate factor of safety.
The crossing involves 2 nos. well foundation locations as exhibited in Figure 4A, 1 no. pile foundation location and 2 nos. anchor tower locations on open cast foundation having depth of 3 meters with total crossing distance of 2.564 km. The Brahmaputra River is the largest river in the Indian sub-continent with very high velocity and 10th largest in the world in terms of discharge and known for its character of shifting its course. Fig: 4A
One of the anchor tower locations on the right bank of the river was 137 meters away from the river bank edge during construction in 2010. Subsequently, because of continuous erosion of the bank the distance reduced to 10 meters in the year 2016 which was 137 meters during 2010 as exhibited in Figure 4B. During the year 2016, this Anchor Tower location also got submerged by river water. Considering the fact that any further shifting of bank line or formation of any whirl pool in this area may cause a problem to the stability of the Anchor Tower foundation, this location was shifted to a safer location with pile foundation as per details indicated below in Table2. Prior to shifting, to protect this location from the continuous river bank erosion, Bamboo Palisading work had to be provided at the river bank face as a temporary protection measure as exhibited in Figure 4C.
For smooth and accident-free work of pile foundation, one of the circuits which was directly above the new pile foundation under construction had to be shifted by using an Emergency Restoration System (ERS) tower as exhibited in Figure 4D. Subsequently, on completion of the pile foundation the entire work of tower erection and final stringing was carried out by keeping one of the circuits continuously charged as per requirement so as to keep the power flow through this line intact. All tower foundations have been designed with adequate factor of safety.
3.4 Adoption of chemical earthing along with provision of Transmission Line Arrestors (TLA) in high isokeraunic level coupled with high soil resistivity
The Silchar- Byrnihat section in the state of Meghalaya, encounters severe lightning in the hilly terrain having high soil resistivity [Reference 3]. Due to which number of outages were experienced in this section during monsoon period in spite of regular maintenance of the section. The main cause of tripping was attributed to the lightning during and on set of monsoons. On measurement of tower footing resistance (TFR) of the section, value of TFR was found high in 129 tower locations.
To minimize the TFR value, sodium bentonite having high moisture characteristics & swelling properties was used as Ground Enhancement Materials. The TFR results improved significantly as exhibited in Figure5. The existing counterpoise earthing trenches were excavated, a layer of about 4 cm of sodium bentonite slurry [Reference 4] applied to the existing counterpoise trenches & the trenches refilled with excavated soil.
As the life of marconite, another Ground Enhancement Material is comparatively higher, NETC is in process to use it on experimental basis. Further, based on experience gained from successful operation of the Transmission Line Arrestors (TLAs) in lightning prone areas for 220kV & 132 kV system in India, use of 400 kV TLAs is considered to be best option to eliminate the issue of outages permanently. NETC is exploring adoption of 400kV Transmission Line Arrestors (TLA) in near future though these are costlier and its successful operational experience are yet to be established in Indian grid.
3.5 Clearance of vegetation at frequent intervals and developing environmental awareness among local people.
The entire North Eastern part of India falls under tropical rain forest zone and the trees and plants grow very fast in these areas. The quickest such growth is observed with Bamboo which covers the entire region. Therefore, along with a schedule of ground patrolling with three cycles in a year i.e., pre-monsoon, post-monsoon and before high-wind season being followed for clearing the vegetation, the line sections traversing through the forest areas are being patrolled regularly. Such practices have minimized the outage of Transmission Lines due to vegetation faults.
In NER, the tribal forest dwellers follow the age-old practice of burning the forest cover for cultivation purpose known as Jhum Cultivation as exhibited in Figure 6. On many occasions, outage of transmission lines had been observed due to such burning. Therefore, to stop such practices the forest dwellers have been educated in collaboration with the local administration, to develop environmental awareness among them. This has considerably reduced the outage of transmission line to a great extent.
In NER, the tribal forest dwellers follow the age-old practice of burning the forest cover for cultivation purpose known as Jhum Cultivation as exhibited in Figure 6. On many occasions, outage of transmission lines had been observed due to such burning. Therefore, to stop such practices the forest dwellers have been educated in collaboration with the local administration, to develop environmental awareness among them. This has considerably reduced the outage of transmission line to a great extent.
3.6 Replacement of disc insulators with polymer insulators and painting of towers with zinc rich anti corrosive paint in polluted area Some towers in Silchar- Byrnihat section are located in the industrial zone of Byrnihat town in Meghalaya, causing flash over due to deposition of industrial dust and subsequent outage of the line. The pollution combined with humidity reduce the surface resistance of porcelain disc insulators which lead to flow of leakage current on the surface. Leakage current with large magnitude flowing on the surface for long period causes degradation of the insulator performance leading to flashovers ultimately thereby effecting the reliability of power supply system.
NETC replaced all porcelain disc insulator strings with Polymer insulators due to the fact that hydrophobicity properties of polymer insulators are best suited in polluted environment.
Due to such heavy pollution in the area, the tower members including the leg members also get severely rusted and corroded causing concern for structure strength. Therefore, Zinc rich paint and anti-pollution paint with necessary primer coat have been provided as preventative measures.
3.7 Asset Monitoring
In addition to regular on-line update on weather condition, physical patrolling of the line to clear any bamboos & vegetation, three cycles of patrolling are done in a year i.e., pre & post monsoon and before high wind season [Reference 5]. Due to climatic and geographical condition of the area and data analysis done so far, NETC have its priorities on the asset, as per following:
i) Foundations- In lands slide area, River bank foundations, low lying areas
ii) Towers- In theft prone area
iii) Insulators- In lightning prone area / polluted / industrial / mining area
iv) Hardwares- In lightning prone area/ high wind / normal
v) Conductors- In river crossings spans/ other areas
vi) Earthwire - In river crossings/ lightning prone areas/ high
vii) Earthing of towers- In lightning prone areas
Due to above, NETC has strengthened the foundations, provided missing members in towers, replaced porcelain disc & composite insulators with polymer insulators, replaced damaged clamps & jumpers, replaced broken strand conductors & earth wire and strengthened earthing conductors. For condition monitoring of insulators, hardware, jumper connection etc., Punctured insulator detection (PID), thermo vision scanning and night patrolling is also taken up. To identify & rectify the fault as per indication of fault locators, tower top emergency patrolling is done on regular basis. The identified vulnerable location, leaning trees on uphill side, land slide areas, mining & blasting prone areas are monitored through monthly inspection. For on line monitoring, data analysis and inspection NETC is exploring use of drone in near future.
NETC is regularly assessing health of its asset through its risk management mechanisms mentioned above. NETC is in process of formulating health index of its assets. Further to manage lifecycle of assets more effectively, getting higher return with the assets and to reduce the total cost of risk, NETC is actively considering certification of ISO 55001.
3.8 Asset Management
The asset is being managed by a group of highly experienced personnel with a Corporate Office headed by a Chief Executive Officer designated as Managing Director. For convenience of maintenance, the Transmission System is divided into three line sections with intervening power substations and each line section is further divided into a number of sub section (2/3) with placement of maintenance teams comprising of experienced fitters/foremen. The team leaders report to the concerned line incharges and carry out patrolling as per the advance planning done .In the vulnerable & most vulnerable stretches of the transmission system having history of component failure, the tower top patrolling is being carried out along with ground patrolling almost on regular basis during adverse climatic conditions. The defects identified during patrolling are categorized as of shutdown and non shutdown nature. The defects of non shutdown nature are attended during regular patrolling and defects of shutdown nature are attended by obtaining shutdown of the respective transmission line or during opportunity shut down being availed by others depending upon the severity of the defects. Safety drill is a regular feature before starting any maintenance activity.
The entire maintenance activity is suitably aided by different protection mechanisms including disturbance recorders, event loggers, phase measuring units etc. put in place in the connected power sub stations and the grid and well supported by the Grid Operators.
4 CHAPTER4- AVAILABILITY OF TRANSMISSION LINE CORRIDOR
NETC has achieved availability factor of transmission corridor above 99.89 % under severe environmental conditions since last five years. Table 3 below exhibits annual availability factor of last five years. As per Central Electricity Regulatory Commission (CERC) regulation [Reference 6], Normative Annual Transmission System Availability Factor (NATAF) is calculated as per following formulae:
AVo (Availability of ‘o’ no. of AC line elements) =
.JPG)
Where,
o = Total number of AC lines.
Wi = Weightage factor for ith transmission line i.e. number of sub-conductors x ckt. km for an AC T/L.
5- CONCLUSIONS
NETC has been successful in maintaining availability of transmission corridor by adopting various innovative and sustainable mitigation measures after identifying the constraints. To reduce the down time, NETC is focusing on new methods of aerial patrolling, remote monitoring, use of modern O&M instruments, advance information about cyclones, earthquake & lightning etc. Use of 400 kV TLAs is one of the measures for future depending on its success in Indian Grid coupled with various stateof-the-art techniques for continuous strengthening of foundations & towers. NETC views human resources as the most precious asset of the company and therefore stresses high importance on mandatory and advanced training programs for upgradation of skill and knowledge.
[This technical paper was presented on November 24, 2021 in CIGRE International Conference at Slovakia, being one of the best papers from Indian transmission line power utility.]
NETC has achieved availability factor of transmission corridor above 99.89 % under severe environmental conditions since last five years. Table 3 below exhibits annual availability factor of last five years. As per Central Electricity Regulatory Commission (CERC) regulation [Reference 6], Normative Annual Transmission System Availability Factor (NATAF) is calculated as per following formulae:
AVo (Availability of ‘o’ no. of AC line elements) =
Where,
o = Total number of AC lines.
Wi = Weightage factor for ith transmission line i.e. number of sub-conductors x ckt. km for an AC T/L.
5- CONCLUSIONS
NETC has been successful in maintaining availability of transmission corridor by adopting various innovative and sustainable mitigation measures after identifying the constraints. To reduce the down time, NETC is focusing on new methods of aerial patrolling, remote monitoring, use of modern O&M instruments, advance information about cyclones, earthquake & lightning etc. Use of 400 kV TLAs is one of the measures for future depending on its success in Indian Grid coupled with various stateof-the-art techniques for continuous strengthening of foundations & towers. NETC views human resources as the most precious asset of the company and therefore stresses high importance on mandatory and advanced training programs for upgradation of skill and knowledge.
[This technical paper was presented on November 24, 2021 in CIGRE International Conference at Slovakia, being one of the best papers from Indian transmission line power utility.]
- Satyajit Ganguly, MD, NETCL
- Harshal Malewar, Deputy Manager, NETCL
REFERENCES
[1] North Eastern Regional Power Committee (NERPC) website for Transmission line corridor in NER
[2] Average annual rainfall of the states from www.rainwaterharvesting.org
[3] IEEE-80: Guide for safety in AC Substation Grounding
[4] Improvement of grounding properties by using bentonite, Proceedings: XXIX Conference CIGRE, Paris, 1982 Veledar, M,Timic, Z. Skok, S. and First, Z
[5] NETC in house document – System Operating Procedure for Operation & maintenance, Internal Document (not for circulation)
[6] Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.
Topics: PS3: Climate change impact on equipment and infrastructure (icing, fire, wind, floods, landslides, etc.) Keywords: Tropical rain forest, Isokeraunic, Random Rubble Masonry, Chemical earthing, Transmission Line Arrestors
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
please contact: contact@energetica-india.net.